CASA-1000 completion postponed to 2024

 

Фотографии: akipress.kg

June 21, 2021, 14:49       Источник akipress.kg       Комментарии

AKIPRESS.COM - CASA-1000 project was launched in 2018 and was supposed to be completed in 2023, but because of the pandemic in 2019-2020, its implementation was suspended, said Deputy Minister of Energy Taalaibek Ibraev. Therefore, the completion date of the project is postponed to 2024, he said.
The Central Asia South Asia Electricity Transmission and Trade Project (CASA-1000) is a project on exporting seasonal surplus electricity from Kyrgyzstan and Tajikistan to cover the growing demand for electricity in Afghanistan and Pakistan.

Ссылка на новость:
https://for.kg/news-707398-en.html

Читайте также

Athletes participating in Tokyo Olympics will have to leave Japan immediately after completion of their competitions

SCO Film Festival postponed

Accrual of interest on CASA-1000 project loan already started

Farid Niyazov was not delivered to courtroom, hearing postponed

Situation in Afghanistan and Pakistan won't affect CASA-1000 project: Deputy Minister

 

SAPE:

 

АГРОПОРТАЛ КЫРГЫЗСТАНА, НОВОСТИ СЕЛЬСКОГО ХОЗЯЙСТВА
Обучение ювелирному делу в Бишкеке
МСН Общественно-политическая газета
Изготовление значков и медалей в Бишкеке

18+

FOR.kg - Кыргызстан новости, пресса

FOR.kg search news service (news aggregator, media aggregator)

Read first Agreement on the use of the FOR.kg search site

When using materials from the FOR.kg - reference to the source is required

For all questions please contact customer support

Top.Mail.Ru
Яндекс.Метрика